Symptom
Failed posting entries(e.g. 261) in app "Reprocess Goods Movements"(COGI) are not removed when cancelling confirmation in scenario of PP-EWM integration.
Environment
SAP S/4HANA Cloud
Reproducing the Issue
- Confirm production order.
- There are failed goods movement entries (e.g. 261) in "Reprocess Goods Movements" COGI.
- Cancel the confirmation.
- The failed entries remain there in COGI.
Cause
The scheduling profile is missing or in the configuration of scheduling profile, the concerned goods movements are not maintained as synchronous in "post synchronously to bin".
Resolution
Set goods movements as synchronous in "post synchronously to bin" in scheduling profile and make sure the scheduling profile is maintained in the order.