Symptom
The process of handling rework in production.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Production Control work center
- Go to Task Control view
- Find required production task
- There is no way to skip the task quantity recording in rework process.
Cause
Currently there is a limitation in recording production without confirming the make task, as its a new production order, it's in turn increases the stock/quantity. Whenever a production order is being created with planned quantity, it gets recorded enhancing the finished good quantity once it is finished.
Resolution
It is recommended to post query in Influence Forum so that Development Colleagues can look in to this.
Register your requirement for this feature on Customer Influence Forum, at https://influence.sap.com/sap/ino/#/campaign/886
Keywords
rework production, limitation, customer influence forum, production , KBA , AP-PE-ORD , Production Order , Problem