Symptom
When trying to staff a new resource to a work package, the employee popup does not display any result if the solution 1KC (Advanced Resource Management - Project-Based Services) is active.
Environment
SAP S/4HANA Cloud
Reproducing the Issue
- Go to "Plan Customer Projects" or "Plan Internal Projects" app.
- Select a project.
- Click Edit and select the Work Packages tab.
- Select a work package.
- Try to staff a resource to a role. The resource does not appear in the Worker pop-up.
Cause
This may be due to the deprecated business catalogs related to the solution 1KC (Advanced Resource Management - Project-Based Services).
These catalogs were deprecated and removed from the business role template SAP_BR_PROJECT_MANAGER_PROF in the SAP S/4 HANA Cloud 2402 release.
This information is available in the What’s new of 2402 release:
https://help.sap.com/docs/SAP_S4HANA_CLOUD/ee9ee0ca4c3942068ea584d2f929b5b1/044d816f22de4197bf3f7044c7836f02.html?locale=en-US&version=2402.500
Resolution
Manually add the following deprecated business catalogs to the Project Manager business role.
- Resource Management - Staff Customer Projects (SAP_CA_BC_RSH_CUSTPROJ_PSP_PC)
- Resource Management - Staff Internal Projects (SAP_CA_BC_RSH_INTPROJ_PSP_PC)
Keywords
Plan Customer Projects, Plan Internal Projects, resource, J11, 1KC, 1A8, Advanced Resource Management, add resource, assign , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem