3434097 - The Resource Network does not work as expected

Symptom

In the PP or DS strategy there is a parameter to consider resource networks. You have set this flag, but the system doesn't seem to consider it. Orders are not scheduled or moved to the resource which is foreseen according to the maintained Resource Network in tx /sapapo/resnet.


Read more...

Product

SAP S/4HANA all versions ; SAP Supply Chain Management all versions

Keywords

/sapapo/resnet, resource network, rescheduling, alternative modes , KBA , SCM-APO-PPS-DST-FCT , Scheduling Functions Detailed Scheduling Planning Board , SCM-APO-PPS-HEU , Heuristics , SCM-APO-MD-RNW , Resource Network , How To