Symptom
Error FCO_AVC_PS004 'There's no budget available for project XXXXXX', ‘XXXXX WBS Element budget exceeded’ while,
- creating a PR/PO.
- posting a document.
- transfering a budget.
Environment
SAP S/4HANA Cloud
Cause
During transferring budget, say if the budget availability control profile PS001 (Maintained in the project master data) was used and then semantic tag ACT_COST (maintained in the SSCUI Maintain Budget Availability Control for Projects) is considered;
Then the available budget of WBS element/ Project definition, is calculated based on planning data for those G/L accounts with semantic tag ACT_COST. If the GL account used for budgeting/planning is not assigned to the semantic tag ACT_COST, then the error obtained as expected.
Resolution
To solve the issue
- maintain semantic tag ACT_COST on the GL account, or
- maintain budget on WBS with G/L Account having the semantic tag ACT_COST .
See Also
Keywords
There's no budget available for project XXXXXX, XXXXX WBS Element budget exceeded, FCO_AVC_PS004, PR, PO creation, PO, PR creation, budget exceeded, S4_1C, S4_PC, actual posting, budget transfer, budget supplement, budget document , KBA , PS-COS-BUD , Budget , CO-OM-CCA , Cost Center Accounting , Problem