SAP Knowledge Base Article - Public

3436483 - Need a Workflow for Project Budget Approval which is uploaded from Import Financial Plan Data app

Symptom

This KBA helps you to guide you on your requirement, "Upon upload of Project Budget from Import Financial Plan Data App, you want to send/submit it for the approval".

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Go to Import Financial Plan Data app in your S/4 Hana Cloud system
  2. Click on Download templates
  3. Select Project Budgeting option to download latest template
  4. Once the relevant budget data is uploaded, you want this budget needs to be sent for approval

Resolution

In order to have approval workflow for the Budget uploads which are uploaded from the Import Financial Plan Data, you can get use of the API Project Budget Approval.

Further this API Document section also has Setup, Configuration & User Guide.

 

See Also

Keywords

Project Budget Approval, Import Financial Plan Data, Budget Approval, S4_PC, S4_1C, F1711. , KBA , CO-FIO-OM-PL-2CL , Planning (Public Cloud) , How To

Product

SAP S/4HANA Cloud Public Edition 2402