SAP Knowledge Base Article - Public

3442752 - The Field Lastchangeddatetime is not updated in Enterprise Project API

Symptom

The field Lastchangeddatetime is not updated when we make any changes to any field in WBS element of a project in app Project Planning.

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Open App Project Control - Enterprise Projects
  2. Select a Project and click on Go button
  3. Go to Related App button
  4. Select Project Planning App
  5. Click on Edit 
  6. Change the Description of the WBS element and Click on Save.
  7. Retrieve the field Lastchangeddatetime using Enterprise project API.

Cause

Standard Behaviour

Resolution

The field LastChangeDateTime is used to check the last change date time of the project header. Any changes in any wbs of a project,will update the field ProjectLastChangedDateTime in the API.

Please refer to the below SAP Help Documentation in which you can find the description of the fields,

A_EnterpriseProject

See Also

API_ENTERPRISE_PROJECT_SRV_0002

Keywords

LastChangeDateTime, API, ProjectLastChangedDateTime, Update, Enterprise Project API, SAP S/4Hana Cloud. , KBA , PS-FIO-2CL , Please use PPM-SCL* , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions