3447186 - Material Cost Estimate change lot size with option "Costs based on"

Symptom

During "Create Material Cost Estimates" (CK11N) or "Display Material Cost Estimates" (CK13N), results are not displayed as expected. There are issues with user entry, costing lot size and UOM (units of measure).  

Environment

SAP S/4HANA Cloud

Cause

When changing the costing lot size in "Create Material Cost Estimates" / "Display Material Cost Estimates" with the parameter 'costs based on', the system is NOT re-calculating the costs based on the new quantity. In fact the system simply scales the result.

This applies for sales order costing, too.

Resolution

Only "Create Material Cost Estimates" really calculates the cost based on a specific lot size. If you cost again the material with "Create Material Cost Estimate" and new lot size, you will get the correct results. Therefore you have to enter new costing lot size on the entry screen of "Create Material Cost Estimate".

See Also

2505352 - CK11N/CK13N change lot size with option 'Costs based on'

Material Cost Estimates

Keywords

CK13N, CK11N, CK51N, CK53N, sales order costing, MTO, cost estimate, user entry, lot size, quantity. , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , CO-PC-PCP , Product Cost Planning , Problem