3448112 - How To Add the Desired Country for Working Day and Holiday Calendar in the Project Scope

Symptom

You are trying to add a country for working day and holiday calendar, but the desired country is not in the list to be added.

Environment

SAP Cloud for Customer

Reproducing the Issue

  1. Go to implementation projects.
  2. Go to current projects.
  3. Open the "First implementation".
  4. Open activity list.
  5. Search for "Working Day Calendar" and open.
  6. Create a new working day or create a holiday.
    (some countries could be missing e.g: US)

Cause

The desired country was not configured and was not added to the scope.

Resolution

  1. Go to Business Configuration work center;
  2. Open Implementation Projects view;
  3. Select the change project;
  4. Click on Edit Project Scope;
  5. Go to step 4 (Questions);
  6. Expand Built-in Services and Support => Business Environment;
  7. Select Units, Rates, and Cross-Application Data;
  8. Select the working day calendars of the countries you require;
  9. Finish the scoping.

Keywords

Working day; holiday calendar; Datatime; country; not available; change country; calendar. , KBA , AP-RC-DT , Date & Time , How To