Symptom
Duration of the Phase in a Project cannot be edited when the duration of the Task is modified
Environment
SAP Business ByDesign
Resolution
Once you change the duration of the Project task, kindly follow the below steps to update the duration of the subsequent Project Phase.
- Go to Project Management work center
- Go to Projects view and search for respective Project ID ABC
- Select the Project Plan tab
- Go to Gantt chart sub tab and click on More(>>) and then Options
- Select the Schedule tab. This will automatically schedule the Phase duration based on the Task duration.
See Also
Kindly refer to the below blog on Project scheduling and its aspects for further information.
Keywords
Project Phase duration update, Schedule the phase duration, phase duration , KBA , SRD-PRO-PMN , Project Management , How To
Product
SAP Business ByDesign 2402