Symptom

When an order was created the costing sheet details were not added.

After there was a posting and it was noticed that the Overhead costs were not calculated.

The costing sheet was then added and now the Overheads need to be recalculated. 

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Create an order without a costing sheet.
  2. Several postings were done on the order.
  3. After it was noticed that the costing sheet was not updated for the order.

Resolution

To reprocess the Overhead Calculation please use the app: 

Schedule overhead accounting jobs 

and run template: Actual Event-Based Overhead Calculation: Reposting/Reversal (SAP)

By inserting the order and posting date or document number this will trigger EB overhead recalculation.

See Also

Schedule Actual Overhead Calculation

Schedule Overhead Accounting Jobs

Keywords

new costing sheet, Event-based, flag, project, WBS, WBS element, orders, service documents, recalculate, reprocess, previously posted document,  , KBA , CO-OM-2CL , Overhead Cost Controlling (Public Cloud) , CO-FIO-CCA-TRA-2CL , Transactions (Public Cloud) , Problem