SAP Knowledge Base Article - Public

3458767 - No warning/error message obtained while creating PO/PR with exceeded budget

Symptom

Even though the Budget Availability Control is active for the project and the all the settings are maintained correctly, no warning/error message obtained as per settings during the creation of Purchase Requisition or Purchase Order.

Environment

SAP S/4HANA Cloud

Cause

Scope item 2I3 not activated.

Resolution

In order to use the functionality of budget availability control and commitments, scope item 2I3 has to be activated.

Raise a case under X4-CBC-PRX to get the scope item 2I3 activated. 

See Also

Predictive Commitments Management

Keywords

Error, warning, budget check, no error/warning, BAC, budget availability control, S4_PC, S4_1C, project , KBA , PS-COS-BUD , Budget , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions