Symptom
Longer wait time while creating/displaying/fetching/updating enterprise project with large project structure.
Environment
SAP S/4HANA Cloud Public Edition
Cause
The performance decreases as the number of WBS elements associated with a enterprise project increases.
Resolution
The recommendation from SAP is to create enterprise project with less than 10 hierarchical levels and less than 2000 WBS Elements.
Further creation of WBS Elements will affect the performance of the app and API while displaying/fetching/creating/updating data.