Symptom
Longer wait time while creating/displaying/fetching/updating enterprise project with large project structure.
Environment
SAP S/4HANA Cloud
Cause
The performance degrades as the no of WBS elements associated with a enterprise project increases.
Resolution
The recommendation from SAP is to create enterprise project with less than 10 hierarchical levels and less than 2000 WBS elements.
Further creation of WBS elements will affect the performance of the app and API while displaying/fetching/creating/updating data.
Keywords
No of WBS elements, enterprise project, Project control, PPM-SCL-STR, PPM-SCL-STR-FIO , KBA , PPM-SCL-STR , Project Structure (Public Cloud) , PPM-SCL-STR-FIO , Fiori UI for Project Structure (Public Cloud) , Problem