SAP Knowledge Base Article - Public

3470718 - Synchronization warning in Solution Manager: 'The task was not processed as its Dictionary Object is not part of the target category'

Symptom

In the synchronization logs from SAP Signavio Process Manager to SAP Solution Manager, the following warning appears: 'The task was not processed as its Dictionary Object is not part of the target category' 

Environment

• Business process model connector for SAP Signavio solutions

Reproducing the Issue

1. Initiate the process model synchronization from SAP Signavio Process Manager to SAP Solution Manager.
2. Observe the warning message: 'The task was not processed as its Dictionary Object is not part of the target category'. in the sync logs.

Cause

The warning occurs when a task in the model is linked to a dictionary category that is not set up in the synchronization project.

Resolution

The warning is displayed on the Signavio side when a task in the model is not connected to the dictionary category set up in the sync project.

For example, the task is linked to a dictionary category other than Activities. The task name and ID are mentioned in the warning message (the ID starts with 'sid').

If you'd like to skip the sync for these tasks, you can remove the dictionary links and create a new project, then sync the process. Tasks with no dictionary link will be skipped in the new project.

If you want to determine which Signavio process the task belongs to, you can use the report 'Process characteristics with element details' in Signavio Process Manager via 'Reporting' > 'Process characteristics with element details' > choose 'Export options' > check the option 'Include IDs'. The IDs mentioned in the warning message can be found in the column 'Signavio ID'.

Keywords

signavio, process manager, spm, solman, solution manager, error, synchronization, synchronisation, bpmc, connector, process step, task, activity, dictionary, category, sync issue, process sync, sync error, dictionary mismatch, task ID, process ID, export options, process characteristics, reporting tool, process model, sync project, Synchronization warning in Solution Manager The task was not processed as its Dictionary Object is not part of the target category , KBA , BPI-SIG-CA-BMB , business process model connector for SAP Signavio solutions , Problem