3476814 - No requirement is created after running MRP

Symptom

After creating a PIR and running MRP, the requirement is displayed for the material, but no sales order, planned order or purchase requisition is created.

Environment

SAP S/4HANA Cloud, Public Edition.

Reproducing the Issue

  1. Create a PIR
  2. Run MRP for the Material
  3. No sales order, planned order or purchase requisition is created

Cause

Gross Requirements Planning is set.

Resolution

MRP is not generating sales order, planned order or purchase requisition, because the requirement is not in the Gross Requirements Planning section, therefore the MRP run will not plan them.

Please refer to this Help Page for more information regarding:

To change to another planning strategy, it's necessary to clear the existing planning data for other strategies first. Please avoid using multiple planning strategies at the same time.

See Also

Gross Requirements Planning

Keywords

MRP Run, MD04, sales order, planned order, purchase requisition,  , KBA , PP-MRP-PR-2CL , Planning Execution (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions