SAP Knowledge Base Article - Public

3478017 - Error "Changing Project Task not possible; field is read-only" While Migrating Open Sales Order

Symptom

While migrating open sales orders below errors are displayed. 

  • Changing Project Task not possible; field is read-only
  • Changing UUID not possible; field is read-only
  • Changing Project Task ID not possible; field is read-only
  • Project task missing
  • Project missing

Environment

SAP Business ByDesign 

Reproducing the Issue

  1. Go to Business Configuration - Overview
  2. Migration of Open Sales Orders
  3. Migrate open sales orders using the migration tool
  4. Execute the migration file

System shows Below error:

  • Changing Project Task not possible; field is read-only
  • Changing UUID not possible; field is read-only
  • Changing Project Task ID not possible; field is read-only
  • Project task missing
  • Project missing

 

 

Cause

Under Items Project Task (Cost and Revenue Assignment) is maintained. 

Resolution

Project Task (Cost and Revenue Assignment) is used for multi customer project or a direct cost project, but the project task assigned is "Service - time and material (project)" (For instance). Those are meant for customer projects with sales integration only. 

Remove the values in Project Task (Cost and Revenue Assignment) and migrate the sales order list.

 

Keywords

error; migrate open sales orders; Changing Project Task not possible; field is read-only; Project task missing. , KBA , AP-SLO-SO , Sales Order , Problem

Product

SAP Business ByDesign all versions