Symptom
Enterprise Project name is not display in task details after clicking on save/submit button for the time entries in Manage My Timesheet App.
Environment
SAP S/4HANA Cloud
Reproducing the Issue
- Go to App "Manage My Timesheet"
- Select the Enterprise project from the task list and book time
- Click on Save/Submit
Resolution
The time recorded by the employee for enterprise projects is posted against the WBS element, activity type, and cost center.
See Also
Keywords
Enterprise project, Task details, Save, Manage my timesheet, Save, Submit, Project name, SAP S/4HANA Cloud, Ca-ts-s4. , KBA , CA-TS-S4 , Cross Application Timesheet in S/4HANA , Problem