Symptom

You noticed that when working with the Project Time Recordings Report, the report does not show the Time Hours from a particular month until the present day.

Environment

SAP Business ByDesign.

Reproducing the Issue

  1. Go to the Project Management work center.
  2. Go to the Reports view.
  3. Select the Report - Project Time recordings.
  4. In the selection enter the the Project ID and Employee ID.
  5. Maintain the affected date.
  6. You see that there is no actual work after a specific month.

Cause

Such scenario occurs due to there is an user whose accounts got terminated and due to there are backend messages stuck in queue. 

Resolution

Please raise a case to SAP as we need to perform a backend correction to fix this scenario.

Keywords

Time Hours, Time Entry, Not Visible, Not Appearing, Not Available, Project Time Recordings, Report, Project, Time Administration. , KBA , AP-TIM , Time and Labour Management , Problem