Symptom
Make-to-order (MTO) production or engineer-to-order (ETO) planning strategies need to be used in MRP areas.
Environment
SAP S/4HANA Cloud Public Edition
Cause
For MTO and ETO scenario, the planning can only be performed in the plant MRP area.
Resolution
MTO and ETO strategies can be used only in the plant MRP area. Therefore, individual customer segments are always in the plant MRP area even if a storage location that refers to a storage location MRP area is assigned in the sales order.
It is not possible to plan individual customer segments in the MRP area.
See Also
SAP Note: 550844 - FAQ: MRP areas
Question 3
Keywords
Make-to-order, MTO, production or engineer-to-order, ETO, plan, MRP, plant MRP area, individual customer segments , KBA , PP-MRP-PR-2CL , Planning Execution (Public Cloud) , How To