Symptom
In Migrate Your Data for migration object Enterprise Project, the Profit Center on the WBS Element is not that from the source file.
Note: The Project Profile is "Project with Revenue".
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open app Migrate Your Data.
- Migrate data for migration object Enterprise Project with a WBS Element structure (Project Profile = Project with Revenue).
- The migration completes successfully.
- Check the structure in Project Planning app, the WBS Element(s) has different Profit Centers to the upload file.
Cause
All the WBS elements in the subtree of a billing element must have the same functional area and profit center as the billing element.
Resolution
This is standard behaviour. If the requirement is for the child WBS Element to have a different Profit Center then review your Billing Element structure.
See Also
SAP Help Work Breakdown Structure Maintenance
SAP Help Billing Element
Keywords
migration, profit center, WBS element, PSP, project planning, project control - enterprise project , KBA , PPM-SCL-STR , Project Structure (Public Cloud) , PS-FIO-STR , Fiori UI for Project Systems-Structures , How To