3487702 - Import financial plan data to WBS elements with Processing Status: Closed

Symptom

Plan data is allowed to be uploaded for closed project via APP 'Import Financial Plan Data'.

Environment

SAP S/4HANA Cloud

Cause

This is current system design, the standard master data checks are limited on plan data and cannot be compared with the checks on actual data.
This is a design decision to make planning as flexible as possible.

Resolution

As a workaround, kindly use the Substitution/Validation Rules Tool to implement own checks and master data validations in S/4HANA Cloud.
See the following documentation link: Validations During Plan Data Import

Keywords

Import Financial Plan Data, ACDOCP, Closed Project, status check. , KBA , CO-FIO-OM-PL-2CL , Planning (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions