3491032 - Material is still costed even with 'Do Not Cost' indicator - SAP S/4HANA Cloud Public Edition

Symptom

Setting the indicator ‘Do Not Cost’ in the material master and expecting the material should not be included in the costing result in “Create Material Cost Estimates” or “Edit Costing Runs”. However, the results show the material is still included. 


Read more...

Environment

SAP S/4HANA Cloud Public Edition

Product

SAP S/4HANA Cloud Public Edition all versions

Keywords

Do Not Cost, Create Material Cost Estimates, CK11N, Edit Costing Runs, CK40N, BOM , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , Problem