3495174 - Required Start date and End date in maintenance order are incorrect after saving

Symptom

Required Start date and End date getting changed when user click on save, but the dates are showing incorrect

Environment

  • SAP S/4HANA Cloud
  • Enterprise Asset Management

Reproducing the Issue

1. Enter app 'Create Maintenance Order' or 'Change Maintenance Order'.

2. Fill in Required Start date and End date in order header, fill in Duration in order operation, click save.

3. Dates are reset and not showing as expected.

Cause

Required date calculation is relevant to settings in SSCUI 104234 - Set Scheduling Parameters and the work duration maintained in operation.

Resolution

Refer to below Community blog:

How the system calculates the "required end date" in mnt order- S4HC public Asset mgmt

*Please note that if you want to change the scheduling type setting in SSCUI 104234 - Set Scheduling Parameters, the changes will NOT impact the existed maintenance orders, only work for new orders.

See Also

Scheduling types in PM order

Scheduling Data

Keywords

Required Start Date, Required End Date, Scheduling Types , KBA , PM-FIO-2CL , Fiori User Interface (UI) for PM (Public Cloud) , How To