Symptom
Required Start date and End date getting changed when clicking on save, but the dates are showing incorrect.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
1. Enter app 'Create Maintenance Order' or 'Change Maintenance Order'.
2. Fill in Required Start date and End date in order header, fill in Duration in order operation, click save.
3. Dates are reset and not showing as expected.
Cause
Required date calculation is relevant to settings in SSCUI 104234 - Set Scheduling Parameters and the work duration maintained in operation.
Resolution
Refer to below Community blog:
How the system calculates the "required end date" in mnt order- S4HC public Asset mgmt
If change the scheduling type setting in SSCUI 104234 - Set Scheduling Parameters, the changes will not impact the existed maintenance orders, only work for new orders.
See Also
Keywords
Required Start Date, Required End Date, Scheduling Types,104234, Set Scheduling Parameters , KBA , PM-FIO-2CL , Fiori User Interface (UI) for PM (Public Cloud) , How To