SAP Knowledge Base Article - Public

3497805 - Integration Center job does not execute on the first day of the schedule

Symptom

In the UI, you would like to schedule an Integration Center job to run daily since a particular day.

You found the job didn't run on the first day according to the schedule. Instead, it starts executing since the next day.

"Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."

Environment

SAP SuccessFactors HCM Suite

  • Integration Center

Reproducing the Issue

1. Integration Center -> My Integrations

2. Open the integration and go to "Scheduling" tab

3. Specify the Start Time by clicking on the clock

Pasted image.png

Cause

There is a issue identified when using the clock to specify the job start time. In some cases, this may lead to the job not running on the first day.

Resolution

As a workaround, please manually enter the job start time in the UI. This would ensure the job runs properly since the first day.

Engineering team is discussing and working to resolve this issue. At this moment there is no ETA for it.

Keywords

SF, Success Factors, IC, configuration, miss, skip, UTC migration, scheduler service, SFINT-18527 , KBA , LOD-SF-INT-INC-JOB , Integration Center Job , Problem

Product

SAP SuccessFactors HCM Core 2405