Symptom
Although a Procurement Lead Time is maintained under the Planning tab in the product master data, when creating purchase request from Purchase Requests and Orders work center, the Planned Order Date and Planned Delivery Date are not as expected considering the maintained procurement lead time.
Environment
SAP Business ByDesign
Reproducing the Issue
- Open the master data of product XYZ (XYZ represents ID).
- Navigate to Planning tab, maintain Procurement Lead Time field (example: 15 days).
- Go to Purchase Requests and Orders work center.
- Create new purchase request by clicking New Purchase Request (Manual).
- Maintain "Delivery Start Date" field, release the purchase request.
- Go to Purchase Requests and Orders work center, Purchase Requests view.
- Click the hyperlink of the purchase request, see that the Planned Order Date is not 15 days ahead of Planned Delivery Date.
Cause
Procurement Lead Time only works in purchase requests that are created from Supply Planning work center, New Proposal common task.
Resolution
To enable the logic of Procurement Lead Time, it is necessary to create purchase requests from the Supply Planning work center instead of creating it in the Purchase Requests and Orders work center.
See Also
Keywords