Symptom
Customer has found that the employment validity check for project roles has been changed and they would like to know how the validity will be checked based on the date.
Environment
SAP S/4HANA Cloud Public Edition 2408
Reproducing the Issue
- Go to the Plan Customer Projects app.
- Add a role and a resource to the project.
Cause
Employment of an employee who is assigned to a SAP delivered role in a professional services project should overlap at-least by one day with the project duration. This is an existing behaviour for Project Manager role. Now it is enhanced to other SAP delivered roles like Project Controller, Project Accountant and Project Partner.
Resolution
- If a project’s duration is from 01.08.2024 to 31.03.2025, and employee ABCD* with employment ID 1234* is valid from 01.01.2024 to 02.08.2024.
- Here in this example, this employment ID is valid to be assigned to project roles as there are 2 days which are overlapping within the project duration.
- If a project’s duration is from 01.08.2024 to 31.03.2025, and employee EFGH* with employment ID 5678* is valid from 01.01.2024 to 30.06.2024.
- Here in this example, this employment ID is not valid to be assigned to project roles as there are no overlapping days within the project duration.
*Where employee ABCD & EFGH are external employee IDs and 1234 & 5678 are the internal IDs of two employees
Keywords
Duration, project, employment, valid, overlapping, project, check, Plan Customer Projects, work package, resource , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem