3507944 - Runtime error occurs when manually exporting Project WBS Elements in APP Concur Integration Setup - SAP S/4HANA Cloud Public Edition

Symptom

Manual exportation of Project WBS Elements takes too long to execute and ends in runtime error.

"Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Access App "Concur Integration Setup".
  2. Click "Project WBS Element".
  3. Click "Manual Export".
  4. Fill export parameter(s).
  5. Click Execute.

Cause

Manual exportation of Project WBS Elements cannot handle the large volume of data to be processed online.

Resolution

Due to the time out issue, manual exportation of Project WBS Elements has to be processed in the backend if there's a large volume of data.

Refer to the following steps and process the job in the backend.

  1. Access App Concur Integration Setup.
  2. Click "Project WBS Element".
  3. Click "Manual Export".
  4. Click "Menu".
  5. Click "Program".
  6. Click "Execute in Background".

Keywords

manual export, WBS Element, Project WBS Element, Concur, fail, failed, too long, runtime error. , KBA , BNS-CON-SE-S4-FIN , Concur S/4HANA Financial Integration , BNS-CON-SE-S4 , Concur Suite Enablement S/4HANA Integration , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions

Attachments

Pasted image.png