Symptom

User is unable to change the status of a WBS Element, after opening its Details using app 'Project Planning'.

"Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Open app 'Project Control - Enterprise Projects' and search for a project;
  2. Select 'Related apps' > 'Project Planning';
  3. Click in 'Edit';
  4. Select any WBS Element in order to open its details;
  5. Notice that it won't be possible to change the Processing status of the WBS Element.

Cause

Once an user selects a WBS Element in the 'Project Planning' app to check its details, the system opens a different extension - named 'WBS Element (F3799)'.

However, since it is only possible to change the status of a WBS Element in the 'Project Planning' app, the 'Processing status' field won't be editable/selectable.

Resolution

To change the Processing Status of a WBS Element, users can select the element in app 'Project Planning', click in Processing Status and choose the desired status.

See Also

For further information on processing status for Projects and related elements, refer to the following link: SAP Help Portal - Processing Status for Projects and WBS Elements.

Keywords

S/4HANA Cloud, projects, enterprise project, wbs element, status, processing status, change, project planning , KBA , PPM-SCL-STR-FIO , Fiori UI for Project Structure (Public Cloud) , How To