Symptom
Freezing Horizon, Calendars and Good Receipt Processing Time were maintained in Transportation Lane Master Data.
Planning run profile “Switchable Constraints” has Distribution Freeze Horizon = Active.
Planning job does not respect these settings from Transportation Lane Master Data, example:
- There were orders inside the freezing horizon period that were changed, deleted, or created.
- Number of working days is different from calendars.
- There were planned elements in non-working days based on calendars.
- Number of Goods Receipt processing days is bigger or smaller then set in master data.
Read more...
Environment
- SAP Supply Chain Management (SCM)
- SAP Integrated Business Planning (SCM-IBP)
Product
Keywords
IBP, Freezing Horizon, Distribution Freeze Horizon, Production Freeze Horizon, Not respected, Changed, Order Based Planning, OBP, goods receipt, shipping calendar, receiving calendar , KBA , SCM-IBP-RM-PLG , Planning , SCM-IBP-RM-OPT , Order-Based Optimizer , SCM-IBP-RM-FH , Order-Based Finite Heuristic , How To