Symptom
In the Materials tab of the new Project creation, system always picks the latest Purchase Order price of the non stock material, irrespective of the price maintained in the Project Period Plan.
Environment
SAP Business ByDesign
Cause
This is the system standard behaviour.
Resolution
As per the current design :
1. Price from latest Purchase Order with reference to the Project -
If a Purchase Order with reference to the Project exists, the system uses the price from that Purchase Order. If there is more than one Purchase Order for the same material, the system uses the price from the latest Purchase Order.
2. Price from latest Purchase Order without reference to the Project -
If there is no Purchase Order with reference to the Project, the system uses the price from a Purchase Order that does not have a reference to the Project. If there is more than one Purchase Order for the same material, the system uses the price from the latest Purchase Order.
Keywords
Purchase order price picked for material in project, period plan price not considered, latest purchase order price considered for material, non stock material in project , KBA , SRD-PRO-PMN , Project Management , Problem