Symptom
After replenishment for production completed, there is nothing changed in corresponding production order.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Production Control work center.
- Access Production Orders view.
- Select a production order which is not finished, click Edit.
- Click button You Can Also, select New Replenishment with Reference.
- Select a product, click Replenish.
- Open the newly-created warehouse request, proceed until replenish task is finished with quantity confirmed.
- Check in this production order, nothing changed.
Resolution
This is system standard behavior. Replenishment with production order as reference will not impact production order or its production task. Its only result is "Goods Movement" - some inventory is moved from one logistics area to another logistics area. The inventory is not allocated to this production order, it can be used for any purpose.
Keywords
Replenishment, Replenish, Production Order , KBA , AP-PE-ORD , Production Order , Problem