3529903 - Cost rate determination for commercial projects.

Symptom

Cost rate determination for commercial projects.

Environment

SAP S/4HANA Cloud Public Edition

Resolution

The cost rate for a demand created in a work package is determined as follows:

The default cost center of the delivery org assigned to the demand is taken along with the activity type while fetching cost rate. If there is no delivery org, then the cost center of the project along with the activity type is taken into consideration for fetching cost rate.

If an employee is staffed then the cost center of the employee is taken into consideration along with the activity type for fetching the cost rate (provided the employee cost center is different).

Keywords

Cost rate, Planned cost, customer projects, Internal projects, demand, work package, CA-CPD-SS. , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , How To