SAP Knowledge Base Article - Public

3532260 - Confirmed quantity is greater than Planned quantity of the production task.

Symptom

When Confirmed Quantity of the Production Order Task Control can be Greater than the Actual Quantity. System Accept it without Displaying any Warning message.

Environment

SAP Business ByDesign

Reproducing the Issue

1. Go to Production Control Work center.
2. Select Task Control view.
3. Enter the Task id and choose confirm button.
4. Enter the quantity more than planned quantity and the system will accept it without displaying any warning message.

Cause

This is a flexible option we have in Business ByDesign, there is no way to restrict it.

Resolution

This is standard behaviour.

Keywords

Production Order, Task Control, Make task, Confirmed quantity, Planned quantity. , KBA , SRD-SCM-WME-PRD , Production Control , Problem

Product

SAP Business ByDesign all versions