Symptom
When doing transformation from BEI to 3F0, it's necessary to make configuration for SSCUI 102431 or 102810.
When doing the configuration error occurs:
"Proc. key RSEBW is event-based but costing sheet 6310PC is not event-based"
Environment
SAP S/4HANA Cloud Public Edition
Cause
It's necessary to change the relevant costing sheets to event-based one.
Resolution
There are 2 solutions:
- Change the Costing Variants from PYG1/PYG2 to PYR1/PYR2
- Change the corresponding costing sheets to event-based one for PYG1/PYG2.
Valuation Variant: PYG1 - 0Y6; PYG2 - 0Y7
Change with SSCUI 102608 Define Valuation Variants per Plant
Change Costing Sheets from like 6310PC to 6310EP.
See Also
Help portal
[Blogs:
采取行动:过渡到 SAP S/4HANA Cloud 中基于事件的生产成本过账3F0 - SAP Community|https://community.sap.com/t5/enterprise-resource-planning-blogs-by-sap/%E9%87%87%E5%8F%96%E8%A1%8C%E5%8A%A8-%E8%BF%87%E6%B8%A1%E5%88%B0-sap-s-4hana-cloud-%E4%B8%AD%E5%9F%BA%E4%BA%8E%E4%BA%8B%E4%BB%B6%E7%9A%84%E7%94%9F%E4%BA%A7%E6%88%90%E6%9C%AC%E8%BF%87%E8%B4%A63f0/ba-p/13574779]
English version:
Transition to Event-Based Production Accounting in... - SAP Community
Keywords
BEI, 3F0, transfer, configuration, 102608, costing sheet. , KBA , CO-PC-OBJ-2CL , Cost Object Controlling (Public Cloud) , Problem