Symptom
- How is the "Key figures" in "Credit Management" are calculated.
- System update wrong calculation in credit segment average days late.
Environment
SAP S/4HANA Cloud Public Edition
Cause
Resolution
- Refer to the help documents "How the Key Figures in Credit Management Are Calculated" link
- Understand that the Average Days Late are calculated with the following logic: (Invoice amount (10€) x Late payment (5 days) + Invoice amount (5€) x Late payment (2 days) / (10€ + 5€) = 4 days).
- Conduct a test run of the report UKM_TRANSFER_KEY from the App Manage Credit Accounts.
- If differences are found in the test run of the update key figure report, schedule the update of Update Payment Behavior Key Figures from the App Schedule Credit Management Jobs using the job template "Update Payment Behavior Key Figures".
See Also
Keywords
Average Days Late, Credit Segment, Incorrect Calculation, Credit Management, Public Cloud, SAP S/4HANA, UKM_TRANSFER_KEY, Update Payment Behavior Key Figures. , KBA , FIN-FSCM-CR-2CL , Credit Management (Public Cloud) , How To