Symptom
When replicating Cost Centers from SAP S/4HANA Cloud Public Edition to SuccessFactor using communication scenario SAP_COM_0056, only the ones created from the last period are replicated, even though there are more than one valid periods.
Environment
SAP S/4HANA Cloud Public Edition
Cause
This is as per system design, since only one single time-slice, which is valid at the key date when you are changing the cost center, will be sent to SF and stored there. Any other time slice will not be transferred to SF.
Resolution
The recommended solution is to use the new replication via MDI, which supports the time slices correctly.
See Also
Keywords
Cost center replication, MDI, communication scenario, SAP_COM_0056, valid period, time-slice. , KBA , CO-FIO-CCA-MD-2CL , Master Data (Public Cloud) , CO-FIO-CCA-MD , Master Data , Problem