Symptom
MRP elements are displayed in Monitor Stock / Requirements List app (MD04) but not in MRP Cockpits, such as Manage Material Coverage app.
Environment
SAP S/4HANA Public Cloud
Cause
The MRP Cockpits behave not exactly the same as Monitor Stock / Requirements List (MD04). It only shows the material coverage situation within a certain period of time, which is the Shortage Evaluation Period. If the available / requirement dates of the MRP elements are beyond the Shortage Evaluation Period, they will not be displayed in the MRP Cockpits.
Resolution
The Shortage Evaluation Period varies for different Material Shortage Definition. By selecting different shortage definition in the app, you can set different Shortage Evaluation Periods. To make the MRP elements displayed in the MRP Cockpits, you should set the Shortage Evaluation Period long enough.
Since the pre-delivered material shortage profile cannot be modified, you should follow below 2 steps to set the Shortage Evaluation Period:
- Create your own material shortage profile in SSCUI 101177 - Define Material Shortage Profiles and set the proper Shortage Evaluation Period.
- Assign the material shortage profile to your user in SSCUI 101917 - Assign Material Shortage Profile to Users.