3537730 - Incorrect status shown in "Manage Material Cost Estimates" app

Symptom

When accessing app "Manage Material Cost Estimates", the status of the cost estimate is 'Costed', even though "Price Update: Other Prices" was executed (Release Material Cost Estimates app). The expectation is that status would be 'Released'.

Environment

SAP S/4HANA Cloud Public Edition

Cause

Correct system behavior.

Resolution

Releasing a standard cost estimate updates the calculated cost to the Standard Price field in the material master. Therefore, in order to have the status 'Released', you have to execute "Price Update: Standard Price" (Release Material Cost Estimates app).

See Also

Marking and Releasing Standard Cost Estimates

Price Update

Keywords

Costed, released, cost estimate, CK11N, price update, standard price, future price, report. , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , CO-PC-PCP , Product Cost Planning , Problem