SAP Knowledge Base Article - Public

3538062 - System Proposing Incorrect Logistics Area During Post Goods Receipt

Symptom

  • The system proposes an incorrect logistics area during the Post Goods Receipt (PGR) against Purchase Order (PO).

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Inbound Logistics work center.
  2. Go to Purchase Orders view.
  3. Find relevant PO ID and select post goods receipt.
  4. Now system proposes incorrect logistics area against the Location maintained in respective purchase order.

Cause

The system operates at the site level according to the hierarchy and strategy selection as per material flow rules however there are no specific settings to configure the logistics area based only on location alone.

Resolution

Kindly update requirement on Customer Influence forum:https://influence.sap.com/sap/ino/#/campaign/886

See Also

2608268 - System is Proposing Wrong Logistics Area While Doing Post Goods Receipt

Keywords

PGR, Post Goods Receipt, Logistics Area, Incorrect, Purchase Order, PO, Material Flow Rules, Site Level, Hierarchy, Strategy Selection. , KBA , AP-IDP , Inbound Delivery Processing , Problem