3544939 - System changes Stock Transfer Proposal to Dependent Demand when released.

Symptom

System changes Stock Transfer proposal to Dependent Demand when released and saved.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Supply Planning Work Center.
  2. Go to Products View.
  3. Find Product ID XXX (XXX means product ID) and Supply Planning Area YYY (YYY means Supply Planning Area ID).
  4. Open and find Production Proposal.
  5. Click Open Material Flow and find Production Proposal for Product ID ZZZ (ZZZ means Product ID).
  6. Expand and notice that there is a Stock Transfer Proposal for Product ID AAA (AAA means Product ID).
  7. Click on Release and Save and the Stock Transfer Proposal changes to Dependent Demand.

Cause

This issue appears because for Product XXX, the Transport Lane BBB (BBB means Transport Lane ID) has Procurement Type as In-House Production.

Resolution

It is necessary to change the Procurement Type to Internal Procurement to system doesn’t change the Stock Transfer proposal to Dependent Demand.