Symptom
When reversing the Technical Completion (TECO) of a production or process order, the originally set basic start and end dates are automatically rescheduled.
Environment
SAP S/4HANA Cloud Public Edition.
Reproducing the Issue
- Technically complete a production order.
- Reverse the technical completion.
- Observe the change in the initially set basic start and end times of the order.
Cause
Standard system behavior
Resolution
Revoking TECO leads to rescheduling of production order. If the order is already confirmed than the confirmed dates are used for scheduling.
Rescheduling during revoke TECO is hardcoded, therefore it is not possible to customize it.
See Also
Keywords
Production order, technical completion, basic start time, basic end time, change, automatic, SAP S/4HANA Cloud Public Edition, Manufacturing, Production Planning and Control, Production Operations, Discrete Manufacturing, process order, teco, dates, revoke , KBA , PP-SFC-CPL-2CL , Order Close (Public Cloud) , PP-PI-POR-2CL , Process Order (Public Cloud) , PP-SFC-2CL , Production Orders (Public Cloud) , Problem