The scheduled job in 'Schedule Mass Creation of Production Version' app is failing with the following error:
- An error occurred. Please create an incident on component PP-PI-MD-PRV.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Go to 'Schedule Mass Creation of Production Version' app;
- Schedule a job;
- Check the job results;
- The job failed.
Cause
The job is failing because there is no restrict selection criteria maintained. This is standard system behavior.
Resolution
For the successful execution of the mass creation in the 'Schedule Mass Creation of Production Version' app, it's essential to maintain restrictions in the job parameters.
Without these restrictions, the job will terminate with error.
Maintain restrictions such as Plant and schedule a new job.