Symptom
Error message 'Maximum allowed total demand or assigned effort was exceeded' (PRP089) is displayed during the creation of a project in app 'Project Control - Enterprise Project'.
Environment
SAP S/4HANA Cloud Public Edition.
Reproducing the Issue
- Open app 'Project Control - Enterprise Projects';
- Click on Create;
- Fill the mandatory fields as needed;
- When confirming the project creation, the error 'Maximum allowed total demand or assigned effort was exceeded' (PRP089) is displayed.
Cause
The Unit of Measures (UoM) defined and called in the backend during the project creation were not found in the system.
Resolution
Review the UoMs defined in Activity/SSCUI 102179 - Unit of Measure, to ensure that all relevant units are correctly configured. The correct Time units are:
- Hours (H);
- Days (D);
- Weeks (W);
- Years (Y).
See Also
Further information on this SSCUI can be found in the following KBA:
Keywords
S/4HANA Cloud, project, project control, enterprise project, create, save, error, prp089, demand, effort, maximum allowed total demand or assigned effort was exceeded, unit of measure, uom , KBA , PPM-SCL-STR-FIO , Fiori UI for Project Structure (Public Cloud) , Problem