Symptom
- The issue arises when attempting to update the status as Blocked for a Planning Area in the Availability Confirmation tab of Material Master.
- The system does not allow the status to be set to Blocked once the Availability Confirmation is made Active for a Planning Area.
Environment
Available To Promise Check Run
Reproducing the Issue
- Navigate to the Product Data Work Center.
- Proceed to the Materials View and choose the sub-view Materials.
- Search and select the relevant material and choose the relevant option.
- Choose the Availability Confirmation tab.
- Attempt to change the Status against a planning area to Blocked.
Cause
- Only values in the fields Availability Check Scope and other fields available in the screen can be changed.
Resolution
- The system is designed such that once the Availability Confirmation is made Active for a Planning Area, the status cannot be set to Blocked.