Symptom
After executing the MRP for a material, the procurement proposals will be created in the net-segment of the planning without assigning them to project stock.
Environment
SAP S/4HANA Cloud Public Edition 2408
Reproducing the Issue
- Create a project material demand using "Manage Project Demand app" with demand type "Project Stock, Reservation".
- Check the Stock/Requirement list
- Procurement proposals has no connection with WBS element.
Cause
MRP live planning currently does not support the planning of manual reservations in a project segment (project stock reservations) effectively.
This limitation is mentioned in release restriction note 3450904 for SAP S/4HANA Cloud 2408, specifically in the chapter related to Project System / Enterprise Portfolio and Project Management.
- The reservation getting generated from Project Demand Type "Project Stock, Reservation" (App ID: F4562) is not relevant for MRP. There are no requirements generated for this reservation after MRP run.
Due to this limitation, it is not possible to plan appropriate project stock reservations using MRP live in CE2408.
Unfortunately the current system behavior is not completely reflected by this statement as right now the MRP live planning considers appropriate reservations as relevant but ignores their assignments to project stock. Based on that procurement proposals will be created in the net-segment of the planning w/o assigning them to project stock.
Resolution
The development team is currently working on resolving the issue with release 2502.
This release is expected to be accessible to customers in February 2025.
Please note that SAP may make changes to the release content without prior notice. You can find the latest information on the S/4HANA upgrade schedule at the Upgrade & Maintenance Schedule page.
See Also
SAP Note 3450904
Keywords
Manage Project Demand app, Project Stock, Reservation, MRP run, Plant Purchase Requirement, WBS segment demand, Fiori UI, Material Requirements Planning, Public Cloud, SAP S/4HANA Cloud 2408, release restriction, manual reservations, project segment, project stock reservations. , KBA , PP-FIO-MRP-2CL , Fiori UI for Material Requirements Planning (Public Cloud) , Known Error