Symptom
It is only possible to have review tasks assigned to leaf members (as they are associated to general tasks).
Is there a way to have review tasks also on node levels through the calendar?
Environment
SAP Analytics Cloud
Cause
This is the expected behavior when using a wizard in the SAP Analytics Cloud calendar to generate tasks and processes from a driving dimension.
Resolution
With the calendar wizard, members that are defined as nodes in the dimension hierarchy will generate processes, leaf members will generate tasks, and the generated tasks are either general tasks and review tasks, or composite tasks.
See Also
Keywords
review task, node, hierarchy, leaf member, process, calendar wizard , KBA , LOD-ANA-PL-PRO , Planning Process, Input Task, Calendar Task , Problem