Symptom
The "Realign Schedules" and "Schedule Production" buttons are grayed out in the "Capacity scheduling board" application.
Environment
SAP S/4HANA Cloud Public Edition
Cause
The buttons like "Realign Schedules" are only available on bottleneck operations. The bottleneck operation is the operation scheduled on the production line work center (pacemaker work center) maintained in the production version details.
Resolution
- Maintain the production line field of the material.
- All the bottleneck order operations scheduled on that work center for that material will then be allowed to be realigned.