Symptom
After Scheduling a Story in SAP Analytics Cloud, the "Dynamic Text" values displayed in the export PDF file were incorrect.
Environment
- SAP Analytics Cloud (2024.02)
- S/4HANA live connection.
Reproducing the Issue
- Login to SAC tenant
- Open the affected story with Prompt variable set to "save current variable selections".
- Create a "Schedule Publication"
>> Scheduling has been successful, Report sent contains the correct data, and the "Dynamic text" values are the same as they were when the report was last saved. - Change data backend (f.g.) Start Date (202401) and End Date (202403)
- Create another "Schedule Publication"
>> Scheduling has been successful for the second schedule attempt, Report sent contains the correct data, however, the "Dynamic Text" variables values have not been updated:
(f.g.) PDF should have the dates in the 'Dynamic Text' as following : Start Date (202401) and End Date (202403). However, the displayed values are: Start Date (202310) and End Date (202312).
Cause
Product defect.
Resolution
A fix was deployed by the development team (Delivery 2025.9)
Keywords
schedule, prompt, number, value, data, file, date, report. , KBA , LOD-ANA-SCH , SAC Story Scheduling and Publication , Problem
Product
SAP Analytics Cloud 1.0