Symptom

The Project Plan Cost for a specific project becomes invisible when attempting to upload a plan cost file for another or same project within the same month and year.

Environment

SAP S/4HANA Cloud Public Edition

Cause

The Plan scope X for 'project definition' was not marked in the import file (3rd line in the import file), but was maintained for year, plan category, etc.

Resolution

  1. Maintain the Plan scope X for 'project definition' in the import file.
  2. Refer to the example scenario explained in the "Examples: Financial Data Import" section for more details.

See Also

How to Import Financial Plan Data

Keywords

Project Plan Cost, Invisible, Upload, Plan Cost File, Same Month and Year, Plan scope X, Project Definition, Import File, SAP S/4HANA Cloud Public Edition, Financial Data Import, disappear. , KBA , PPM-SCL-REP , Project Reporting (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions