Symptom
The Project Plan Cost for a specific project becomes invisible when attempting to upload a plan cost file for another or same project within the same month and year.
Environment
SAP S/4HANA Cloud Public Edition
Cause
The Plan scope X for 'project definition' was not marked in the import file (3rd line in the import file), but was maintained for year, plan category, etc.
Resolution
- Maintain the Plan scope X for 'project definition' in the import file.
- Refer to the example scenario explained in the "Examples: Financial Data Import" section for more details.