Symptom

You are using the Data Source PROPRJU04 in a customized report but cannot find where the data (such as Earliest Finish Date and Latest Start Date) are getting pulled from when it comes to Milestones. 

Environment

SAP Business ByDesign

Reproducing the Issue

WoC Business Analytics 

Data Sources View

Search the Data Source PROPRJU04

Under Views, search and add the fields bellow:

-Latest Finish Date

-Latest Start Date

-Earliest Finish Date 

-Earliest Start Date 

Add a Project ABC execute the report.

Under the 4 mentioned fields, you can see some data for the Project's Milestone and you want to know where these data are coming from.

Cause

When opening the related Project ABC, select the Milestone of your choice, select the Scheduling tab, from here you cannot find the Data shown in the report

These data are getting pulled from the related Parent task and can be seen under its Scheduling tab.

Resolution

This is the expected system behavior.